Process

Timeline

Step 1

Developer or Contractor contacts WYEcon about their project

Step 2

WYEcon gets RFP or generates a preliminary design to scope the project

Step 3

WYEcon generates proposal, quote, and estimated schedule for the scope of work

Step 4

Contract negotiations and signing

Step 5

Utility Coordination, Detailed design, long lead-time component procurement, and site work and construction permits are started

Step 6

Construction, storage, and field office equipment and worker mobilization – procured component delivery to job-site

Step 7

Construction starts and is completed

Step 8

Completed system inspections, check out testing, and verification

Step 9

Utility testing, connection, and commissioning

Step 10

Project is placed into service and turned back over to Developer

Step 11

BOOK AN APPOINTMENT